Kilifi Town Water Supply Project

KIL-WTR-001

Completed Water & Sanitation Kilifi Town
KES 45,000,000.00
Total Budget
Completion Progress 55%
Project Description

Improvement of water supply infrastructure in Kilifi Town

Start Date
Jan 15, 2024
End Date
Jun 30, 2025
Contractor
Kilifi Water Services
Funding Source
County Government
Location
Kilifi Town
Constituency
Kilifi North
Project Milestones
Feasibility Study
Target: Feb 15, 2024
Completed
Pipeline Construction Phase 1
Target: Aug 30, 2024
In_progress
Budget Allocations
Financial Year Allocated Released Expenditure Utilization
2024/2025 KES 45,000,000.00 KES 30,000,000.00 KES 25,000,000.00 56%